W. 20th Avenue – Vance to Teller streets
        
        
        Project Description
The traffic signal at the intersection of W. 20th Ave. and Teller St. will be replaced and new sidewalk and ADA compliant curb ramps will be added on the south side of W. 20th Ave. from west of Vance St. to east of Teller St. to connect the sidewalk gap in this area. Storm sewer pipes will also be added to help mitigate drainage issues in the area.
October 2025 Update
Recently Completed Work
Construction of major items for the project is currently on-hold while easements are acquired for the new storm sewer network.
Current Work
Current construction activities include potholing existing utilities at the intersection of W. 20th Ave. and Teller St., which is required to confirm existing utility locations before installation of the new traffic signals and associated wiring.
Upcoming Work
It is anticipated that construction of the major project items will resume by the end of October, beginning with the installation of the new storm sewer pipes.
Traffic Impacts
Current traffic control includes lane closures at the intersection of W. 20th Ave. and Teller St. to facilitate the potholing work. Once storm sewer construction begins, additional traffic control will be installed along W. 20th Ave. to provide a safe working area for the contractor. Two lanes of traffic will remain open during this phase of construction.
Target Project Completion
Major construction activities on the roadway are expected to be completed by the end of December. Final site restorations and landscaping will then occur in the Spring of 2026. Significant lane closures should be completed by this time, but periodic lane closures may occur to allow the contractor to access elements along the roadway.