Reclamite Program

  • Project typeReclamite Asphalt Rejuvenator
  • Project scheduleJune - August 2020
  • Contractor namePavement Restoration Inc.
  • Completion DateAugust 31, 2020
A Pavement Restoration vehicle.

 

 

 

 

    

What can I expect?

During the application process you will begin to see no parking signs placed 24 hours in advance of work being performed.

Once work has begun in your area, one side of the street will be closed at a time to allow the contactor to spray the product down. This product comes out pink until it starts to break, and you will see that the product will start to turn clear. At this point the contractor will apply sand to the road to cover the material up. Once sand has been applied the contractor will open the sanded side of the road and begin work on the opposite side of the road.

After completion of the road the contractor will come back the following day to sweep up the sand on the street.

It is normal for some product to spill onto the concrete. When this happens, you will see a yellowish tint on the concrete. Please allow for some time to pass and the product will fade away. If this remains an issue, please contact the city inspector so the contractor can resolve the issue.

Please make sure to follow all traffic control and flaggers on the project to maintain a safe working environment for both you and the contractor.

You will have access to your home during construction, but we please ask that you avoid driving on the product until sand has been applied or unless instructed by a member of the project.

What is Reclamite?

Reclamite is another asphalt preservation that the City of Lakewood has been using to maintain your roads.

This product helps to reduce oxidization and minimize minor cracking that causes asphalt roads to fall apart.

The City has been using this product for several years now to maintain your roads and extend the life of them. By doing this we can minimize disturbance to the public and reduce the cost of a mill and overlay.

If you have any issues with the product tracking or sand sticking to your vehicle, please contact the contractor. They will be able to resolve the issue for you.

If you have any further questions or concerns about the project, please feel free to contact our construction inspector.

During this process streets will continue to remain available to all emergency services.

2020 Reclamite Resurfacing Map(PDF, 2MB)