Glennon Heights Pool Renovation

  • Project typeRenovation
Glennon Heights Pool

The Glennon Heights Pool is closed for renovation and will not open for the 2019 summer season. The large pool will receive pool shell enhancements and other important improvements to ensure that residents can enjoy it as a place to play and exercise for years to come.

For construction efficiency and cost savings, the work will require a full closure of the facility.

When the renovation project is complete, the facility will feature:

  • A fully accessible bathhouse, which will include a new entry configuration, locker rooms with toilets, sinks and showers, family changing rooms, lockers, additional storage space and a lifeguard office.

  • The existing baby pool with the addition of a zero-depth entry access point required to bring the pool into ADA compliance, which also facilitates expansion of the deck and allows for a better experience for caregivers. This shallow area will include a gentle bubble water feature which is appealing to babies and toddlers. The baby pool will be accessible via a ramp from the renovated bathhouse and stairs.

Stay up to date on the project by checking this page throughout the summer and fall season. 

Progress Update: March 2020

New bathhouse walls are up and roof is under construction. Concrete has been poured in the pool area.


Glennon March 25 (3).jpg



Progress Update: January 2020

The new bathhouse walls are being built and forms are being set for the baby pool.

Glennon pool site January 2020.

Progress Update: October 2019

The new bathhouse foundation has been poured and residents will soon see the block walls being built.

Other important structural improvements are also in progress.

Glennon Heights pool construction October 2019.

 

Progress Update: August 14, 2019

 

Demolition of the Glennon bathhouse went quickly, the contractor finished ahead of schedule. The new bathhouse contractor will begin after Labor Day. Neighboring residents will notice activity on site the week of August 19 as the pool shell enhancements and other important improvements begin.

 

The project is on schedule for completion ahead of the May 2020 pool season.

Glennon heights pool area under renovation.

Location

10600 W. Virginia Ave., Lakewood, CO 80226, Lakewood, CO 80226  View Map

Google Map