RESOLUTION: 2002-83
SUBJECT: Intergovernmental Agreement with the Colorado Department of Transportation for the Union Boulevard Pavement Reconstruction Project.
RECOMMENDATION: It is recommended that City Council authorize an agreement with the Colorado Department of Transportation for the Union Boulevard Pavement Reconstruction Project.
FUNDING SOURCE: Capital Improvement Program.
SUMMARY AND BACKGROUND OF SUBJECT MATTER: In February of 2002, the City submitted the Union Boulevard Pavement Reconstruction Project to DRCOG for TIP funding. The project includes rebuilding of the pavement from 6th Avenue to Alameda Avenue as well as replacement of 3 traffic signals and installation of traffic surveillance cameras at 3 locations. It also includes construction of a right turn lane on southbound Union, from 6th Avenue to 4th Avenue, to help alleviate the congestion that occurs in this area. The total cost for design and construction of the project is estimated to be $3,510,000.
The City was successful in receiving 50% matching TIP funding for this project, and the project has been included in the 2003-2008 State Transportation Improvement Plan with construction scheduled for 2003. The City of Lakewood is the lead organization for completing the design and construction of the project. Funding for Lakewood's 50% share of the project cost ($1,755,000) is budgeted in the 2002 Revised and 2003 City of Lakewood Capital Improvement Program.
RESOLUTION ADOPTION DATE: November 25, 2002
ORIGINATED BY: Public Works Department
STAFF PERSON RESPONSIBLE: Chris J. Jacobsen
Infrastructure Maintenance/Operations Engineer 303-987-7951
DOCUMENTS ATTACHED: Resolution 2002-83
SUBMITTED BY:
Richard J. Plastino, Director of Public Works
REVIEWED BY:
Joni Inman, Director Mayor and City Manager's Office
Michael J. Rock, City Manager
|
|
||
Americans with Disability Act (ADA) Notice |
||